Precautions for installing hollow plastic formwork column structure

Hollow plastic formwork column structure is a new type of construction structure, which has the characteristics of light weight, high strength, waterproof, fireproof V2 level, corrosion resistance, etc., and is widely used in various construction projects. During the installation process of the hollow plastic formwork column structure, construction workers are required to follow certain steps to ensure its installation quality and stability.

First, the construction workers need to eject the vertical and horizontal lines and side lines according to the design requirements to determine the position and size of the column. Then, install the first column formwork in place and use temporary support or lead wire (above No. 14) to tie and fix the main reinforcement to ensure the stability and verticality of the column.

Then, the construction workers need to install and fix the second formwork and use sponge strips (thickness of 2mm) to glue the joints to ensure the sealing and waterproofness of the column. At the same time, support and fix the second formwork, and so on to create a square barrel shape. During the installation process, it is necessary to pay attention to the position and direction of each formwork to ensure the integrity and stability of the column.

After the installation of the column is completed, the construction workers need to use hoops to fix it from bottom to top to ensure the structural stability and load-bearing capacity of the column. At the same time, the deviations of the axis, vertical, diagonal, section, etc. need to be calibrated to ensure the precision and accuracy of the column. Finally, the size of the column is calibrated and finally fixed to ensure the installation quality and stability of the column.

During the installation of the hollow plastic formwork column structure, the following points need to be noted:

1. The position and size of the column must be determined and marked according to the design requirements to ensure the accuracy and stability of the column.

2. The position and direction of each piece of formwork must be installed correctly to ensure the integrity and stability of the column.

3. The main reinforcement of the column must be tied and fixed to ensure the stability and verticality of the column.

4. The joints of the column must be bonded with sponge strips to ensure the sealing and waterproofness of the column.

5. The structure of the column must be fixed with hoops to ensure the structural stability and load-bearing capacity of the column.

6. The precision and accuracy of the column must be calibrated to ensure the installation quality and stability of the column.

In short, the installation process of the hollow plastic formwork column structure requires construction workers to follow certain steps to ensure the quality and stability of its installation. In actual projects, it is necessary to pay attention to every detail and link to ensure the installation quality and stability of the column, and provide protection for the safety and reliability of the construction project.

BZ hollow plastic formwork factory looking forward to your inquiry!